MIS.DCS.0502-07 TEXAS DEPARTMENT OF TRANSPORTATION PAGE 1 AVERAGE LOW BID UNIT PRICES BY DISTRICT SAN ANGELO DISTRICT 7 MAINTENANCE ITEM NO DESCRIPTION UNITS MARCH 31, 2013 . . . TWELVE-MONTH-MOVING . . . QUANTITY AVG BID QUANTITY AVG BID USAGE 100 SERIES 100 2001 PREPARING ROW AC 0.540 2,000.00000 0.540 2,000.00000 1 100 2002 PREPARING ROW STA 66.100 475.16445 3 104 2009 REMOVING CONC (RIPRAP) SY 22.600 20.00000 22.600 20.00000 1 104 2022 REMOVING CONC (CURB AND GUTTER) LF 44.000 30.00000 44.000 30.00000 1 104 2028 REMOVING CONC (MISC) SY 2.000 250.00000 51.000 69.85294 2 110 2001 EXCAVATION (ROADWAY) CY 408.000 20.55000 1 112 2001 SUBGRADE WIDENING (ORD COMP) STA 954.400 84.55754 2 132 2001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 190.000 40.00000 286.000 41.00699 2 132 2004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 514.000 27.39000 1 150 2002 BLADING HR 56.000 167.22321 3 164 2003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 11,253.000 0.20235 2 164 2036 DRILL SEEDING (PERM) (RURAL) (CLAY) AC 2.230 985.70852 1 200 SERIES 216 2001 PROOF ROLLING HR 3.340 61.11976 1 247 2042 FL BS (CMP IN PLC)(TY A GR 2)(FNAL POS CY 47.000 110.00000 1 247 2044 FL BS (CMP IN PLC)(TY A GR 4)(FNAL POS CY 11,105.000 48.35000 1 247 2082 FL BS (CMP IN PLC)(TY A GR 2) TON 16,018.000 19.77000 1 247 2342 FL BS (CMP IN PLACE)(TY A GR 2)(8") SY 8,188.000 11.61000 1 275 2001 CEMENT TON 731.000 111.93000 1 275 2011 CEMENT TREAT(EXIST MATL)(8") SY 56,470.000 1.56000 1 276 2094 CM TRT(PT MX)(CL N)(TY A)(GR 2)(FN POS CY 54.000 170.00000 1 300 SERIES 310 2001 PRIME COAT (MC-30) GAL 9,574.000 5.73865 2 310 2023 PRIME COAT (AE-P, SS-1 OR MS-2) GAL 11,043.000 4.33000 1 316 2025 ASPH (CRS-2P OR CRS-1P) GAL 18,530.000 4.16000 1 316 2221 AGGR(TY-PB GR-3 SAC-B) CY 581.700 99.48620 2 316 2223 AGGR(TY-PB GR-4 SAC-B) CY 871.800 113.14858 3 316 2407 ASPH(AC-3 OR AC-5) GAL 5,236.000 4.76000 1 316 2706 ASPH (TIER II) GAL 251,993.000 2.88500 1 316 2707 ASPH (TIER III) GAL 357,345.000 2.54252 2 316 2709 AGGR (GR 4) CY 14,791.000 44.98000 1 316 2714 ASPH (AC-10-2TR,AC-15P OR AC-20-5TR) GAL 16,678.000 3.97000 1 330 2002 LRA PAV TY-I GR-A TON 46.000 350.00000 1 330 2006 LRA PAV TY-I GR-D TON 196.000 251.35204 2 354 2020 PLANE ASPH CONC PAV(0" TO 1") SY 17.300 80.00000 1 360 2001 CONC PVMT (CONT REINF-CRCP)(8") SY 236.000 190.00000 1 360 2067 SAWCUT (CONCRETE) LF 728.000 5.00000 1 360 2071 CONC PVMT (CONT REINF-CRCP)(6"), SY 133.000 107.65000 1 400 SERIES 400 2001 STRUCT EXCAV CY 63.000 50.00000 1 400 2005 CEM STABIL BKFL CY 17.000 155.00000 1 401 2001 FLOWABLE BACKFILL CY 63.000 250.00000 1 403 2001 TEMPORARY SPL SHORING SF 654.000 20.00000 1 MIS.DCS.0502-07 TEXAS DEPARTMENT OF TRANSPORTATION PAGE 2 AVERAGE LOW BID UNIT PRICES BY DISTRICT SAN ANGELO DISTRICT 7 MAINTENANCE ITEM NO DESCRIPTION UNITS MARCH 31, 2013 . . . TWELVE-MONTH-MOVING . . . QUANTITY AVG BID QUANTITY AVG BID USAGE 400 SERIES 420 2001 CL A CONC (MISC) CY 16.600 390.00000 16.600 390.00000 1 420 2013 CL C CONC (MISC) CY 1.400 550.00000 1 420 2124 CL S CONC(SLAB) SF 118.000 35.00000 1 428 2002 CONC SURF TREAT (CLASS II) SY 2,500.000 5.00000 1 429 2008 CNC STR REP (VERTICAL OR OVERHEAD) SF 1,370.000 85.64708 2 429 2009 CNC STR REP (BRDG DECK)(PARTIAL DEPTH) SF 60.000 60.00000 1 429 2010 CNC STR REP (BRDG DECK)(FULL DEPTH) SF 209.300 96.14668 2 429 2011 CNC STR REP (REMOVE & REPLACE) CY 9.300 1,483.87097 2 430 2010 CL C CONC FOR EXT STRU(CULV)(5'X 5') LF 20.000 550.00000 1 430 2135 CL C CONC FOR EXT STRU (CULV)(2-6'X3') LF 28.330 880.00000 1 432 2001 RIPRAP (CONC)(4 IN) CY 164.000 350.00000 164.000 350.00000 1 432 2002 RIPRAP (CONC)(5 IN) CY 5.600 380.00000 6.800 402.94118 2 432 2008 RIPRAP (STONE TY R)(GROUT)(8 IN) CY 42.000 269.87000 1 432 2027 RIPRAP (SPECIAL) CY 227.000 200.00000 1 432 2030 RIPRAP (CONC)(CL C) CY 63.311 700.00000 1 432 2035 RIPRAP (CONC)(6 IN) CY 8.000 480.00000 1 432 2039 RIPRAP (MOW STRIP)(4 IN) CY 9.000 750.00000 1 432 2066 RIPRAP (CONC)(CL B) CY 17.500 275.00000 17.500 275.00000 1 438 2002 CLEAN AND SEAL EXIST JOINTS LF 325.000 40.00000 1 450 2196 RAIL (TY T552 R) LF 342.000 72.00000 1 452 2003 REMOV RAIL (CONC POST & MTL ELEMENTS) LF 425.000 20.00000 1 462 2008 CONC BOX CULV (5 FT X 4 FT) LF 138.000 550.00000 1 466 2008 WINGWALL (SW-0)(HW=6 FT) EA 2.000 5,200.00000 1 466 2021 WINGWALL (FW-0)(HW=5 FT) EA 2.000 8,500.00000 1 466 2034 WINGWALL (FW-S)(HW=4 FT) EA 2.000 3,800.00000 1 467 2157 SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1)(C) EA 1.000 6,200.00000 1.000 6,200.00000 1 467 2158 SET (TY I)(S= 5 FT)(HW= 4 FT)(6:1)(C) EA 1.000 6,200.00000 1.000 6,200.00000 1 496 2016 REMOV STR (PIPE) EA 6.000 850.00000 1 496 2031 REMOV STR (CATTLE GUARD) EA 1.000 1,496.49000 1 500 SERIES 500 2001 MOBILIZATION LS 1.000 30,000.00000 15.000 28,962.40000 15 502 2001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 1,500.00000 54.000 2,150.39630 15 506 2016 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 78.000 16.57000 1 506 2019 CONSTRUCTION EXITS (REMOVE) SY 78.000 4.88000 1 506 2024 BACKHOE WORK (EROSION & SEDM CONT) HR 10.000 107.06000 1 506 2034 TEMPORARY SEDIMENT CONTROL FENCE LF 500.000 3.71000 1 512 2010 PORT CTB (DES SOURCE)(SAFETY SH)(TY 1) LF 240.000 45.00000 1 512 2011 PORT CTB (DES SOURCE)(SAFETY SH)(TY 2) LF 90.000 100.00000 1 512 2019 PORT CTB (MOVE)(SAFETY SH)(TY 1) LF 300.000 15.00000 1 512 2020 PORT CTB (MOVE)(SAFETY SH)(TY 2) LF 90.000 90.00000 1 512 2028 PORT CTB (STKPL)(SAFETY SH)(TY 1) LF 540.000 33.88889 2 512 2029 PORT CTB (STKPL)(SAFETY SH)(TY 2) LF 90.000 100.00000 1 512 2054 PORT CTB (DES SOURCE)(F-SHAPE)(TY 4) LF 750.000 20.00000 1 512 2055 PORT CTB (MOVE)(F-SHAPE)(TY 4) LF 750.000 12.00000 1 512 2056 PORT CTB (STOCKPILE)(F-SHAPE)(TY 4) LF 750.000 20.00000 1 529 2010 CONC CURB AND GUTTER (TY II)(REINF) LF 48.000 45.00000 48.000 45.00000 1 531 2024 CONC SIDEWALK (5") SY 873.000 60.00000 873.000 60.00000 1 MIS.DCS.0502-07 TEXAS DEPARTMENT OF TRANSPORTATION PAGE 3 AVERAGE LOW BID UNIT PRICES BY DISTRICT SAN ANGELO DISTRICT 7 MAINTENANCE ITEM NO DESCRIPTION UNITS MARCH 31, 2013 . . . TWELVE-MONTH-MOVING . . . QUANTITY AVG BID QUANTITY AVG BID USAGE 500 SERIES 531 2054 CURB RAMPS SY 23.900 200.00000 23.900 200.00000 1 540 2002 MTL W-BEAM GD FEN (STEEL POST) LF 1,329.000 22.11889 2 540 2005 TERMINAL ANCHOR SECTION EA 4.000 250.00000 1 540 2011 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 9.000 1,750.00000 1 542 2001 REMOVING METAL BEAM GUARD FENCE LF 1,413.000 0.98461 2 542 2002 REMOVING TERMINAL ANCHOR SECTION EA 8.000 75.50000 2 542 2003 RM MTL BM GD FEN TRANS (THRIE-BEAM) EA 1.000 100.00000 1 542 2004 REMOVING MTL BM GD FEN TRANS (TL2) LF 100.000 1.50000 1 544 2002 GUARDRAIL END TREATMENT (MOVE & RESET) EA 1.000 1,100.00000 1 544 2013 GDRAIL END TRT(INSTALL)(HBA POST) EA 9.000 2,322.22222 2 545 2001 CRASH CUSH ATTEN (INSTL) EA 2.000 750.00000 1 545 2002 CRASH CUSH ATTEN (MOVE & RESET) EA 2.000 700.00000 1 545 2003 CRASH CUSH ATTEN (REMOVE) EA 2.000 750.00000 1 545 2046 CRASH CUSH ATTEN (INSTAL)(ABSORB 350) EA 1.000 3,500.00000 1 545 2048 CRASH CUSH ATTEN (REMOVE)(ABSORB 350) EA 1.000 2,500.00000 1 545 2049 CRASH CUSH ATTEN (INSTL)(WORK ZONE) EA 2.000 1,300.00000 1 545 2050 CRASH CUSH ATTEN(MOV&RESET)(WORK ZONE) EA 3.000 750.00000 1 545 2051 CRASH CUSH ATTEN (REMOVE)(WORK ZONE) EA 3.000 500.00000 1 600 SERIES 644 2001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 5.000 1,050.00000 1 644 2056 RELOCATE SM RD SN SUP & AM TY 10BWG EA 3.000 350.00000 13.000 811.53846 2 644 2058 RELOCATE SM RD SN SUP & AM TY S80 EA 1.000 1,900.00000 1 644 2060 REMOVE SM RD SN SUP & AM EA 2.000 200.00000 1 658 2258 INSTL DEL ASSM (D-SW)SZ (TYC)CTB EA 9.000 100.00000 1 658 2328 REMOVE DELIN & OBJECT MARKERS ASSMS EA 4.000 25.00000 1 662 2096 WK ZN PAV MRK REMOV (W) 36" (YLD TRI) EA 8.000 100.00000 1 662 2113 WK ZN PAV MRK SHT TERM (TAB) TY W EA 793.000 0.01000 1 662 2115 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 14,575.000 0.04424 3 666 2030 REFL PAV MRK TY I (W) 8" (DOT)(100MIL) LF 94.000 3.00000 1 666 2036 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 1,409.000 1.45000 1 666 2048 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 11,595.000 4.35000 1 666 2153 REF PAV MRK TY II (W) 8" (SLD) LF 376.000 0.44000 1 666 2157 REF PAV MRK TY II (W) 24" (SLD) LF 229.000 3.00000 1 666 2189 PAVEMENT SEALER 4" LF 2,030.000 0.45000 1 666 2191 PAVEMENT SEALER 8" LF 235.000 1.25000 1 666 2195 PAVEMENT SEALER 24" LF 7,912.000 1.00000 1 668 2105 PREFAB PAV MRK TY C (W) (24") (SLD) LF 28.000 26.88000 1 668 2106 PREFAB PAV MRK TY C (W) (ARROW) EA 11.000 195.00000 1 668 2107 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 2.000 275.00000 1 668 2112 PREFAB PAV MRK TY C (W) (RR XING) EA 15.000 575.00000 1 668 2116 PREFAB PAV MRK TY C (W) (WORD) EA 11.000 225.00000 1 668 2118 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 26.000 54.61538 2 672 2012 REFL PAV MRKR TY I-C EA 549.000 4.26230 2 672 2015 REFL PAV MRKR TY II-A-A EA 10,737.000 2.81924 3 677 2001 ELIM EXT PAV MRK & MRKS ( 4") LF 260.000 2.00000 1 677 2003 ELIM EXT PAV MRK & MRKS ( 8") LF 542.000 3.00000 1 677 2005 ELIM EXT PAV MRK & MRKS (12") LF 1,086.000 3.00000 1 MIS.DCS.0502-07 TEXAS DEPARTMENT OF TRANSPORTATION PAGE 4 AVERAGE LOW BID UNIT PRICES BY DISTRICT SAN ANGELO DISTRICT 7 MAINTENANCE ITEM NO DESCRIPTION UNITS MARCH 31, 2013 . . . TWELVE-MONTH-MOVING . . . QUANTITY AVG BID QUANTITY AVG BID USAGE 600 SERIES 677 2007 ELIM EXT PAV MRK & MRKS (24") LF 5,523.000 3.75000 1 677 2008 ELIM EXT PAV MRK & MRKS (ARROW) EA 13.000 35.00000 1 677 2009 ELIM EXT PAV MRK & MRKS (DBL ARROW) EA 4.000 55.00000 1 677 2014 ELIM EXT PAV MRK & MRKS (RR XING) EA 17.000 75.00000 1 677 2018 ELIM EXT PAV MRK & MRKS (WORD) EA 10.000 55.00000 1 677 2020 ELIM EXT PAV MRK & MRKS (36")(YLD TRI) EA 17.000 25.00000 1 677 2021 ELIM EXT (RAISED PAVEMENT MARKERS) EA 212.000 2.00000 1 700 SERIES 712 2005 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 1,214.307 449.84229 4 730 2001 STRIP MOWING AC 51,586.000 25.26243 22 730 2002 FULL-WIDTH MOWING AC 32,312.000 34.20249 14 770 2001 REPAIR RAIL ELEMENT (W-BEAM) LF 3,200.000 13.50000 1 770 2002 REPAIR RAIL ELEMENT (THRIE-BEAM) LF 40.000 8.00000 1 770 2003 REP RAIL ELMNT(THRIE-BM TRANS TO W-BM) LF 20.000 8.00000 1 770 2006 REALIGN POSTS EA 80.000 20.00000 1 770 2007 REPAIR OF TERMINAL ANCHORS POSTS EA 2.000 1.00000 1 770 2008 REPLACE TERMINAL ANCHOR POSTS EA 2.000 1.00000 1 770 2009 REMOVE GDRAIL END TRT/ REPL WITH SGT EA 15.000 2,100.00000 1 770 2010 REPL SINGLE GDRAIL TERM IMPACT HEAD EA 9.000 800.00000 1 770 2011 REPLACE SINGLE GDRAIL TERMINAL RAIL LF 200.000 25.00000 1 770 2012 REPLACE SINGLE GDRAIL TERMINAL POST EA 20.000 30.00000 1 770 2014 REPAIR STEEL POST WITH BASE PLATE EA 15.000 30.00000 1 770 2018 REM/REPL TIMBER POST W/O CONC FND EA 75.000 100.00000 1 770 2019 REM/REPL STEEL POST W/O CONC FND EA 50.000 40.00000 1 770 2020 REM/REPL TIMBER POST W/CONC FND EA 20.000 40.00000 1 770 2021 REM/REPL STEEL POST W/CONC FND EA 50.000 50.00000 1 770 2022 REM & RESET SGT IMPACT HEAD EA 20.000 100.00000 1 770 2023 REPLACE SGT OBJECT MARKER EA 4.000 1.00000 1 770 2024 REPLACE SGT CABLE ANCHOR EA 4.000 1.00000 1 770 2025 REPLACE SGT CABLE ASSEMBLY EA 4.000 1.00000 1 770 2026 REPLACE SGT STRUT EA 4.000 1.00000 1 770 2027 REMOVE & REPLACE BLOCKOUT EA 20.000 10.00000 1 770 2028 REPLACE HINGED TOP SGT STEEL POST EA 20.000 70.00000 1 770 2035 REPAIR RAIL ELEMENT (CURVED RAIL) LF 250.000 16.00000 1 776 2001 REPAIR (STEEL POST W/ W-BEAM-T101) LF 50.000 20.00000 1 776 2004 REPAIR(STL POST W/DOUBLED W-BEAMS-T6) LF 50.000 30.00000 1 776 2011 REP METAL POST W/BASE PLATE (T101 RAIL EA 15.000 10.00000 1 776 2014 REP METAL POST W/BASE PLATE (T6 RAIL) EA 10.000 10.00000 1 1100 SERIES 1122 2001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 200.000 30.00000 1 1122 2009 ROCK FILTER DAMS (REMOVE) LF 100.000 10.00000 1 1122 2037 TEMPORARY SEDIMENT CONTROL FENCE INSTL LF 1,232.000 6.05000 1 1122 2049 BIOGRD EROSN CONT LOGS (18" DIA)INSTAL LF 200.000 5.00000 1 1122 2057 TEMPORARY SEDIMENT CONTROL FENCE REMOV LF 1,232.000 1.39000 1 MIS.DCS.0502-07 TEXAS DEPARTMENT OF TRANSPORTATION PAGE 5 AVERAGE LOW BID UNIT PRICES BY DISTRICT SAN ANGELO DISTRICT 7 MAINTENANCE ITEM NO DESCRIPTION UNITS MARCH 31, 2013 . . . TWELVE-MONTH-MOVING . . . QUANTITY AVG BID QUANTITY AVG BID USAGE 4100 SERIES 4191 2001 CARBON FIBER REINF POLY CONC STRENGTHE SF 10,664.000 28.25000 1 5000 SERIES 5049 2001 BIODGRD EROSION CONTROL LOGS (8" DIA) LF 160.000 6.50000 1 5049 2002 BIODGRD EROSION CONTROL LOGS (18" DIA) LF 120.000 8.20000 240.000 7.38500 2 5900 SERIES 5953 2001 CATTLE GUARD EA 1.000 11,827.82000 1 6000 SERIES 6055 2001 IN-LANE OR TRANSVERSE RUMBLE STRIP LF 80.000 22.00000 1 6800 SERIES 6834 2001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 40.000 31.20000 1 8200 SERIES 8251 2006 RE PM W/RET REQ TY I(W)4"(SLD)(100MIL) LF 31,788.000 0.49000 1 8251 2015 RE PM W/RET REQ TY I(Y)4"(BRK)(100MIL) LF 2,420.000 0.51000 1 8251 2018 RE PM W/RET REQ TY I(Y)4"(SLD)(100MIL) LF 26,293.000 0.85278 2 8251 2025 RE PM W/RET REQ TY II (W) 4" (BRK) LF 7,930.000 0.15000 1 8251 2026 RE PM W/RET REQ TY II (W) 4" (SLD) LF 1,023,771.000 0.13155 2 8251 2029 RE PM W/RET REQ TY II (Y) 4" (BRK) LF 123,830.000 0.14156 2 8251 2030 RE PM W/RET REQ TY II (Y) 4" (SLD) LF 380,107.000 0.13430 2 8600 SERIES 8648 2001 TEMPORARY TRAFFIC SIGNALS LS 1.000 2,900.00000 1